BRIEF CASE FACTS

Client:

G.C.:

Kenaidan Contracting Ltd.

Geotechnical:

Structural:

Piles:

134

Loadings:

Load: 1050kN (236 kips)

Challenges:

Oakville Southwest WWTP

Oakville, ON, Canada

Oakville Southwest Waste Water Treatment Plant required a major expansion of two additional waste treatment facilities. Buoyancy control in the form of rock anchors was required to tie down the deep tanks due to the high water table. EBS mobilized compact equipment to be lowered into the excavations to install the rock anchors.

Load: 1050kN (236 kips)
Depth: 10.2 metres
Total Number of Rock Anchors: 134 double corrosion protected