Emergency Slope Stabilization
- Location
- Toronto
Road closure on Glenwood Crescent in Toronto caused by slope failure of the ravine required immediate emergency restoration. Terraprobe was contracted by the City of Toronto to complete a geotechnical investigation and design the slope stabilization repair. Terraprobe confirmed there was no further slope movement and that damage occurred in a localized area. EBS was contacted to supply and install Helical Anchors to stabilize the existing slope.
Tension Load: 80 kN (18 kips)
Depth: 4 to 14 metres
Total Number of Anchors: 59 Chance® Helical Anchors